4.4 Checklist for Design & Construction of Slab-on-Grade Foundations

This checklist serves as a chapter summary, helps review the completeness of construction drawings and specifications, and provides general guidance on project management. The checklist could be used many ways. For example, use one set of blanks during design and the second set during construction inspection. Note that not all measures are necessary under all conditions. Use different symbols to distinguish items that have been satisfied (+) from those that have been checked but do not apply (x). Leave unfinished items unchecked.

OVERALL SLAB CONSTRUCTION

General considerations. Slab floors require advance planning for plumbing and electrical service. They generally minimize moisture and radon hazard but make detection of termite intrusions especially difficult. Expansive soils require special measures.

____ ____

Elevate slab above existing grade

____ ____

Provide minimum 4-inch-thick aggregate drainage layer under slab

____ ____

Locate plumbing to be cast in slab

____ ____

Locate electrical service to be cast in slab

____ ____

Locate gas service to be cast in slab

SITEWORK

____ ____

Locate building at the highest point if the site is wet

____ ____

Define “finish subgrade” (grading contractor), “base grade” (construction contractor), “rough grade” level before topsoil is respread, “finish grade” (landscape contractor)

____ ____

Establish elevations of finish grades, drainage swales, catch basins, foundation drain outfalls, bulkheads, curbs, driveways, property corners, changes in boundaries

____ ____

Establish grading tolerances

____ ____

Provide intercepting drains upgrade of foundation if needed

____ ____

Locate dry wells and recharge pits below foundation level

____ ____

Establish precautions for stabilizing excavation

____ ____

Establish limits of excavation and determine trees, roots, buried cables, pipes, sewers, etc., to be protected from damage

____ ____

Confirm elevation of water table

____ ____

Determine type and dimensions of drainage systems

____ ____

Discharge roof drainage away from foundation

____ ____

Remove stumps and grubbing debris from site

____ ____

Provide frost heave protection for winter construction

____ ____

Call for test hole (full depth hole in proposed foundation location)

____ ____

Locate stakes and benchmarks

____ ____

Strip and stock pile topsoil

____ ____

Define spoil site

FOOTINGS

____ ____

Unless using a frost protected shallow foundation (FPSF) design, position bottom of footing at least 6 inches below frost depth around perimeter (frost wall at garage, slabs supporting roofs, other elements attached to structure).

____ ____

Confirm adequacy of footing sizes

____ ____

Do not fill the overexcavated footing trench

____ ____

Install longitudinal reinforcing

____ ____

Reinforce footing at spans over utility trenches

____ ____

Do not bear footings partially on rock (sand fill)

____ ____

Do not pour footings on frozen ground

____ ____

Indicate minimum concrete compressive strength after 28 days

____ ____

Call out elevations of top of footings and dimension elevation changes in plan

____ ____

Use keyway or steel dowels to anchor foundation walls

____ ____

Dimension stepped footings according to local codes and good practice (conform to masonry dimensions if applicable)

____ ____

Provide a capillary break between footing and stemwall

STRUCTURAL

____ ____

Avoid ledge-supported slabs unless structurally reinforced

____ ____

Place isolation joints at frost wall, columns, footings, fireplace foundations, mechanical equipment pads, steps, sidewalks, garage and carport slabs, drains

____ ____

Check that partition load does not exceed 500 pounds per linear foot on unreinforced slab

____ ____

Call out depressed bottom of slab where top is depressed

____ ____

Reinforce slab at depressions greater than 1-1/2 inch

____ ____

Use wire chairs or precast pedestals to support welded wire mesh reinforcing

____ ____

Compact fill under slab

 

 

Determine general concrete specifications:

____ ____

Minimum compressive strength after 28 days

____ ____

Maximum water/cement ratio. Note: add no water at site

____ ____

Allowable slump

____ ____

Acceptable and unacceptable admixtures

____ ____

Dampening of subgrade prior to pour

____ ____

Determine form-release agents acceptable to WPM (waterproof membrane) manufacturer if used

____ ____

Establish curing requirements (special hot, cold, dry conditions)

____ ____

Establish surface finish requirements and preparation for WPM (plug all form tie holes)

____ ____

For shrinkage control: use horizontal reinforcing at top of wall and/or control joints

____ ____

Design width of wall to resist height of fill, seismic loads, and loads transmitted through soil from adjacent foundations

____ ____

Use two-way reinforcing (horizontal and vertical) for strength, watertightness, termite and radon resistance

____ ____

Establish anchor bolt depth and spacing requirements, and install accordingly

____ ____

Determine brick shelf widths and elevations

FLOOR SLAB

____ ____

Determine minimum compressive strength after 28 days

____ ____

Determine maximum water/cement ratio. (Note: add no water at site)

____ ____

Determine allowable slump

____ ____

Determine acceptable and unacceptable admixtures

____ ____

Establish curing requirements (special hot, cold, dry conditions)

____ ____

Determine surface finish

____ ____

Provide shrinkage control: WWF (welded wire fabric) reinforcement or control joints

____ ____

Provide isolation joints at wall perimeter and column pads

____ ____

Provide vapor retarder under slab

____ ____

Compact fill under slab

BACKFILLING AND COMPACTION

____ ____

Establish condition of fill material (if site material stays in clump after soaking and squeezing in hand, do not use as backfill)

____ ____

Determine proper compaction

____ ____

Cap backfill with an impermeable cover

MOISTUREPROOFING

General considerations. Since slab on grade foundations do not contain below-grade living space, the key consideration is isolating the interior of the building from ground moisture.  This can be accommodated with a variety of membranes, liquid applied materials, and gaskets.  In all cases, provide a continuous vapor retarder directly under the slab.

____ ____

Isolate the slab from the ground with appropriate waterproofing membranes or other materials

____ ____

Place a polyethylene vapor retarder under floor slabs

For more information visit Water Managed Foundations within the Building America Solution Center.

THERMAL AND MOISTURE CONTROLS

General considerations. Heat loss rate is greatest at the exposed slab edge or frost wall above grade, and at the floor perimeter. Continuity of insulation is difficult except for exterior placement. Horizontal exterior insulation reduces frost penetration depth.

____ ____

Verify that wall insulation R-value and depth meet local codes at a minimum

____ ____

If used, specify exterior insulation product suitable for in-ground use

____ ____

Install protective coating for exterior insulation

____ ____

Install infiltration sealing gasket and through-wall termite shield under sill plate

For more information visit Minimum Thermal Bridging within the Building America Solution Center.

DECAY AND TERMITE CONTROL MEASURES

General considerations. Strategy: (1) Isolate wood members from soil by an air space or impermeable retarder; (2) expose critical areas for inspection. Pressure-treated lumber is less susceptible to attack, but is no substitute for proper detailing. Termite shields are not reliable retarders unless installed correctly.

____ ____

Reinforce slab

____ ____

Remove all grade stakes, spreader sticks, wood embedded in concrete during pour

____ ____

Do not disturb treated soil prior to concreting

____ ____

Avoid ducts beneath floor slab top surface

____ ____

Specify pressure-treated wall sole plates and sleepers

____ ____

Pressure-treat sill plates, rim joists, wood members in contact with foundation walls and floors

____ ____

Pressure-treat all outdoor weather-exposed wood members

____ ____

Install dampproof membrane and through-wall termite shield under sill plate (flashing or sill seal gasket)

____ ____

Elevate sill plate minimum 8 inches above exterior grade

____ ____

Elevate wood posts and framing supporting porches, stairs, decks, etc., above grade (6-inch minimum) on concrete piers

____ ____

Elevate wood siding, door sills, other finish wood members at least 6 inches above grade (rain splash protection)

____ ____

Separate raised porches and decks from the building by 2-inch horizontal clearance or provide proper flashing (for drainage and termite inspection)

____ ____

Pitch solid surface porches, decks, patios for drainage (minimum 1/4 in/ft)

____ ____

Detail slab porch and patios to prevent termite access to superstructure (structural slab over inspectable crawl space)

____ ____

Treat soil with termiticide, especially with insulated slab

RADON CONTROL MEASURES

General considerations. The potential for radon hazard is present in all buildings. Check state and local health agencies for need of protection. Strategies include: (1) passively or actively depressurizing soil and crawl space air pressure relative to the indoors; (2) soil gas retarding membranes; (3) provisions to activate passive soil depressurization systems. Since radon is a gas, its rate of entry through the foundation depends on suction due to stack effect, HVAC system imbalances, exhaust devices, and air leakage especially at high points in the building envelope

____ ____

Reinforce slab

____ ____

Remove all grade stakes, spreader sticks, wood embedded in concrete during pour

____ ____

Form perimeter wall joint with trough, fill with pour-in sealant

____ ____

Place vapor retarder under slab

____ ____

Caulk joints around pipes and conduits

____ ____

Place minimum 4-inch-thick layer of coarse, clean gravel under the slab

____ ____

Separate outdoor intakes for combustion devices

____ ____

Install air retarder wrap around building envelope

____ ____

Seal around flues, chases, vent stacks, attic stairs

PLANS, CONTRACTS, AND BUILDING PERMITS

____ ____

Plans and specs

____ ____

Bid package

____ ____

Establish contractual arrangements (describe principals, describe the work by referencing the blueprints and specs, state the start/completion dates, price, payment schedule, handling of change orders, handling of disputes, excavation allowance, and procedure for firing)  Use signoff on work statements, work ready, and work finished quality assurance procedures.

____ ____

Building permits

SITE INSPECTIONS DURING CONSTRUCTION

____ ____

After excavation and before concrete is poured for the footings

____ ____

After the footings have been poured before foundation wall construction

____ ____

After foundation construction and dampproofing before rough framing

____ ____

After rough framing

____ ____

After rough plumbing

____ ____

After rough electrical

____ ____

After insulation installation before drywall and backfilling in case of exterior insulation

____ ____

Final