This checklist serves as a chapter summary, helps review the completeness of construction drawings and specifications, and provides general guidance on project management. The checklist could be used many ways. For example, use one set of blanks during design and the second set during construction inspection. Note that not all measures are necessary under all conditions. Use different symbols to distinguish items that have been satisfied (+) from those that have been checked but do not apply (x). Leave unfinished items unchecked.
OVERALL SLAB CONSTRUCTION
General considerations. Slab floors require advance planning for plumbing and electrical service. They generally minimize moisture and radon hazard but make detection of termite intrusions especially difficult. Expansive soils require special measures.
____ ____ |
Elevate slab above existing grade |
____ ____ |
Provide minimum 4-inch-thick aggregate drainage layer under slab |
____ ____ |
Locate plumbing to be cast in slab |
____ ____ |
Locate electrical service to be cast in slab |
____ ____ |
Locate gas service to be cast in slab |
SITEWORK
____ ____ |
Locate building at the highest point if the site is wet |
____ ____ |
Define “finish subgrade” (grading contractor), “base grade” (construction contractor), “rough grade” level before topsoil is respread, “finish grade” (landscape contractor) |
____ ____ |
Establish elevations of finish grades, drainage swales, catch basins, foundation drain outfalls, bulkheads, curbs, driveways, property corners, changes in boundaries |
____ ____ |
Establish grading tolerances |
____ ____ |
Provide intercepting drains upgrade of foundation if needed |
____ ____ |
Locate dry wells and recharge pits below foundation level |
____ ____ |
Establish precautions for stabilizing excavation |
____ ____ |
Establish limits of excavation and determine trees, roots, buried cables, pipes, sewers, etc., to be protected from damage |
____ ____ |
Confirm elevation of water table |
____ ____ |
Determine type and dimensions of drainage systems |
____ ____ |
Discharge roof drainage away from foundation |
____ ____ |
Remove stumps and grubbing debris from site |
____ ____ |
Provide frost heave protection for winter construction |
____ ____ |
Call for test hole (full depth hole in proposed foundation location) |
____ ____ |
Locate stakes and benchmarks |
____ ____ |
Strip and stock pile topsoil |
____ ____ |
Define spoil site |
FOOTINGS
____ ____ |
Unless using a frost protected shallow foundation (FPSF) design, position bottom of footing at least 6 inches below frost depth around perimeter (frost wall at garage, slabs supporting roofs, other elements attached to structure). |
____ ____ |
Confirm adequacy of footing sizes |
____ ____ |
Do not fill the overexcavated footing trench |
____ ____ |
Install longitudinal reinforcing |
____ ____ |
Reinforce footing at spans over utility trenches |
____ ____ |
Do not bear footings partially on rock (sand fill) |
____ ____ |
Do not pour footings on frozen ground |
____ ____ |
Indicate minimum concrete compressive strength after 28 days |
____ ____ |
Call out elevations of top of footings and dimension elevation changes in plan |
____ ____ |
Use keyway or steel dowels to anchor foundation walls |
____ ____ |
Dimension stepped footings according to local codes and good practice (conform to masonry dimensions if applicable) |
____ ____ |
Provide a capillary break between footing and stemwall |
STRUCTURAL
____ ____ |
Avoid ledge-supported slabs unless structurally reinforced |
____ ____ |
Place isolation joints at frost wall, columns, footings, fireplace foundations, mechanical equipment pads, steps, sidewalks, garage and carport slabs, drains |
____ ____ |
Check that partition load does not exceed 500 pounds per linear foot on unreinforced slab |
____ ____ |
Call out depressed bottom of slab where top is depressed |
____ ____ |
Reinforce slab at depressions greater than 1-1/2 inch |
____ ____ |
Use wire chairs or precast pedestals to support welded wire mesh reinforcing |
____ ____ |
Compact fill under slab |
|
|
Determine general concrete specifications:
____ ____ |
Minimum compressive strength after 28 days |
____ ____ |
Maximum water/cement ratio. Note: add no water at site |
____ ____ |
Allowable slump |
____ ____ |
Acceptable and unacceptable admixtures |
____ ____ |
Dampening of subgrade prior to pour |
____ ____ |
Determine form-release agents acceptable to WPM (waterproof membrane) manufacturer if used |
____ ____ |
Establish curing requirements (special hot, cold, dry conditions) |
____ ____ |
Establish surface finish requirements and preparation for WPM (plug all form tie holes) |
____ ____ |
For shrinkage control: use horizontal reinforcing at top of wall and/or control joints |
____ ____ |
Design width of wall to resist height of fill, seismic loads, and loads transmitted through soil from adjacent foundations |
____ ____ |
Use two-way reinforcing (horizontal and vertical) for strength, watertightness, termite and radon resistance |
____ ____ |
Establish anchor bolt depth and spacing requirements, and install accordingly |
____ ____ |
Determine brick shelf widths and elevations |
____ ____ |
Determine minimum compressive strength after 28 days |
____ ____ |
Determine maximum water/cement ratio. (Note: add no water at site) |
____ ____ |
Determine allowable slump |
____ ____ |
Determine acceptable and unacceptable admixtures |
____ ____ |
Establish curing requirements (special hot, cold, dry conditions) |
____ ____ |
Determine surface finish |
____ ____ |
Provide shrinkage control: WWF (welded wire fabric) reinforcement or control joints |
____ ____ |
Provide isolation joints at wall perimeter and column pads |
____ ____ |
Provide vapor retarder under slab |
____ ____ |
Compact fill under slab |
BACKFILLING AND COMPACTION
____ ____ |
Establish condition of fill material (if site material stays in clump after soaking and squeezing in hand, do not use as backfill) |
____ ____ |
Determine proper compaction |
____ ____ |
Cap backfill with an impermeable cover |
MOISTUREPROOFING
General considerations. Since slab on grade foundations do not contain below-grade living space, the key consideration is isolating the interior of the building from ground moisture. This can be accommodated with a variety of membranes, liquid applied materials, and gaskets. In all cases, provide a continuous vapor retarder directly under the slab.
____ ____ |
Isolate the slab from the ground with appropriate waterproofing membranes or other materials |
____ ____ |
Place a polyethylene vapor retarder under floor slabs |
For more information visit Water Managed Foundations within the Building America Solution Center.
THERMAL AND MOISTURE CONTROLS
General considerations. Heat loss rate is greatest at the exposed slab edge or frost wall above grade, and at the floor perimeter. Continuity of insulation is difficult except for exterior placement. Horizontal exterior insulation reduces frost penetration depth.
____ ____ |
Verify that wall insulation R-value and depth meet local codes at a minimum |
____ ____ |
If used, specify exterior insulation product suitable for in-ground use |
____ ____ |
Install protective coating for exterior insulation |
____ ____ |
Install infiltration sealing gasket and through-wall termite shield under sill plate |
For more information visit Minimum Thermal Bridging within the Building America Solution Center.
DECAY AND TERMITE CONTROL MEASURES
General considerations. Strategy: (1) Isolate wood members from soil by an air space or impermeable retarder; (2) expose critical areas for inspection. Pressure-treated lumber is less susceptible to attack, but is no substitute for proper detailing. Termite shields are not reliable retarders unless installed correctly.
____ ____ |
Reinforce slab |
____ ____ |
Remove all grade stakes, spreader sticks, wood embedded in concrete during pour |
____ ____ |
Do not disturb treated soil prior to concreting |
____ ____ |
Avoid ducts beneath floor slab top surface |
____ ____ |
Specify pressure-treated wall sole plates and sleepers |
____ ____ |
Pressure-treat sill plates, rim joists, wood members in contact with foundation walls and floors |
____ ____ |
Pressure-treat all outdoor weather-exposed wood members |
____ ____ |
Install dampproof membrane and through-wall termite shield under sill plate (flashing or sill seal gasket) |
____ ____ |
Elevate sill plate minimum 8 inches above exterior grade |
____ ____ |
Elevate wood posts and framing supporting porches, stairs, decks, etc., above grade (6-inch minimum) on concrete piers |
____ ____ |
Elevate wood siding, door sills, other finish wood members at least 6 inches above grade (rain splash protection) |
____ ____ |
Separate raised porches and decks from the building by 2-inch horizontal clearance or provide proper flashing (for drainage and termite inspection) |
____ ____ |
Pitch solid surface porches, decks, patios for drainage (minimum 1/4 in/ft) |
____ ____ |
Detail slab porch and patios to prevent termite access to superstructure (structural slab over inspectable crawl space) |
____ ____ |
Treat soil with termiticide, especially with insulated slab |
RADON CONTROL MEASURES
General considerations. The potential for radon hazard is present in all buildings. Check state and local health agencies for need of protection. Strategies include: (1) passively or actively depressurizing soil and crawl space air pressure relative to the indoors; (2) soil gas retarding membranes; (3) provisions to activate passive soil depressurization systems. Since radon is a gas, its rate of entry through the foundation depends on suction due to stack effect, HVAC system imbalances, exhaust devices, and air leakage especially at high points in the building envelope
____ ____ |
Reinforce slab |
____ ____ |
Remove all grade stakes, spreader sticks, wood embedded in concrete during pour |
____ ____ |
Form perimeter wall joint with trough, fill with pour-in sealant |
____ ____ |
Place vapor retarder under slab |
____ ____ |
Caulk joints around pipes and conduits |
____ ____ |
Place minimum 4-inch-thick layer of coarse, clean gravel under the slab |
____ ____ |
Separate outdoor intakes for combustion devices |
____ ____ |
Install air retarder wrap around building envelope |
____ ____ |
Seal around flues, chases, vent stacks, attic stairs |
PLANS, CONTRACTS, AND BUILDING PERMITS
____ ____ |
Plans and specs |
____ ____ |
Bid package |
____ ____ |
Establish contractual arrangements (describe principals, describe the work by referencing the blueprints and specs, state the start/completion dates, price, payment schedule, handling of change orders, handling of disputes, excavation allowance, and procedure for firing) Use signoff on work statements, work ready, and work finished quality assurance procedures. |
____ ____ |
Building permits |
SITE INSPECTIONS DURING CONSTRUCTION
____ ____ |
After excavation and before concrete is poured for the footings |
____ ____ |
After the footings have been poured before foundation wall construction |
____ ____ |
After foundation construction and dampproofing before rough framing |
____ ____ |
After rough framing |
____ ____ |
After rough plumbing |
____ ____ |
After rough electrical |
____ ____ |
After insulation installation before drywall and backfilling in case of exterior insulation |
____ ____ |
Final |